Did that job make money? Tracking costs against the job's value

How a building firm can tell whether a job made money: what to count, when to check, and why the answer is usually lower than the quote suggested.

You finished the job, the customer paid, and the bank balance went up. That is not the same as the job making money. Plenty of firms find out months later, when the year's accounts come back thinner than the work felt.

This post is about the business side: what to count against a job, when to look, and how to keep it simple enough that it gets done. It doesn't cover pricing the work. You know your trade.

Start with the number you are measuring against

Profit on a job is the value of the job minus what it cost you. So you need to be clear on "value" first.

  • The quote is where you start.
  • Variations change it. Extras add to the value and omissions take away. If an extra was done but never recorded, the job's value on paper is too low and its costs are real. That job looks worse than it was, or worse, you never get paid for it.
  • Credit notes reduce it.

The value is the quote plus agreed variations, less anything credited. Costs are measured against that figure, not against the original quote.

What counts as a cost

Count everything that was spent because of that job.

  1. Materials. Merchant orders, items bought on a card, and things collected on the way to site. The receipts in the van footwell are the ones that go missing.
  2. Your own team's labour. Days on site multiplied by what a day really costs you, not what you pay on the payslip. Include employer's National Insurance, pension and holiday pay.
  3. Subcontractors. Whatever you agreed to pay them, including their extras.
  4. Plant, skips, waste and delivery. Small each time, large across a job.
  5. Anything you had to come back and fix. A snag visit is a cost of the job, even though nobody invoices it.

What about overheads?

Rent, insurance, vehicles, office wages and software are not a cost of any one job, but the firm has to cover them. Two ways to handle it, and either is fine if you stick to it:

  • Work out your overheads for the year and divide them across the days your team works. Add that day rate to each job.
  • Keep job profit as "before overheads" and compare the total of all job profits with your overheads at the end of each month.

If you never do either, you can have a year of jobs that each "made money" and a firm that didn't.

When to look

Looking once, after the final invoice, is too late to change anything. Look at three points.

Before you start. Write down the costs you expect, split into materials, labour and subcontractors. That is the number you will compare against.

While it is live. You don't need profit yet, because half the costs haven't landed. What you need is costs so far against the job's value. If 70% of the value has been spent and the job is half done, you want to know that this week, not at the end.

When it is complete. Add up everything, including late merchant invoices and subcontractor bills that arrive after you have left site. Then compare actual against expected, line by line.

Worked example

This is an example with round figures, not a real job.

ExpectedActual
Job value (quote plus one agreed extra)£40,000£41,500
Materials£14,000£15,200
Own team labour£10,000£11,800
Subcontractors£6,000£6,000
Plant, skips, delivery£1,000£1,500
Total cost£31,000£34,500
Profit before overheads£9,000 (22%)£7,000 (17%)

Profit here is £41,500 minus £34,500, which is £7,000. As a share of the job's value that is about 17%, not the 22% you planned. If your overheads run at 15% of turnover, what is left is about 2%.

Nothing went disastrously wrong on this job. Materials crept up, two extra days went on labour, and the skips cost more than allowed. Those three small things took five points off the margin. That is how it normally goes.

Where the numbers go wrong

  • Labour is guessed, not recorded. If nobody writes down who was on site and for how long, your labour cost is whatever you remember. Get days recorded as they happen, by the supervisor, from the phone.
  • Receipts arrive late or never. Make "photo the receipt before you leave the merchant" the rule. A receipt photographed that day is worth more than one found in a glovebox in March.
  • Extras are done but not recorded. The cost is on the job and the value isn't. Record the variation before the work, even if only as a message to the office.
  • Costs are filed to the wrong job. One merchant order covering three sites needs splitting at the time.
  • Late bills. Don't mark a job as finished until the subcontractors and merchants have all sent what they are going to send.

Keeping it in one place

A spreadsheet works while you have a handful of jobs and one person keeping it tidy. It stops working when the costs sit with the site team, the merchant bills with the office and the quote with you.

In Trojan CRM, one record carries a job from quote to invoice: labour (your own team and subcontractors), materials and receipts are tracked against the job's value, site supervisors record days on site, photos and receipts from their phone without seeing the job's money, and variations go onto the invoice once. While a job is live you see costs so far against its value and its profit so far; the profit is final once the job is complete.

A habit worth having

At the end of every job, spend ten minutes on one question: where did actual differ from expected, and is that a one-off or a pattern? If materials are over on every job, your pricing is wrong. If labour is over on every job, your estimates of days are wrong. Fix the pattern, and the next quote is better than the last.

See it working

Book a demo

We'll walk a job from quote to invoice, using the kind of work your firm does.

Book a demo
Talk to a person

Questions about pricing, set-up or moving off spreadsheets. Tell us how many people will sign in and we'll tell you what it costs.

Email us